RSW's 14-gate Concourse E expansion enters final year of construction
Southwest Florida International Airport's new 14-gate concourse is about two years into construction with roughly 12 to 14 months left, putting the opening around the 2027-28 holiday season, Lee Port Authority CEO Steve Hennigan said. The roughly $1 billion project comes as the airport set a record of 1.5 million passengers in March and says it is short on capacity in peak season.